| Date Posted | Summary |
| 4/13/07 | Virtually complete. Awaiting inspection. |
| 3/16/07 | Decks and exterior trim continues. |
| 3/9/07 | Interior trim continues. |
| 2/23/07 | Interior trim continues. |
| 2/16/07 | Decks, insulation, and interior finishing continues. |
| 2/9/07 | Decks, insulation, and interior finishing continues. |
| 1/26/07 | Installation and interior construction continues. |
| 1/19/07 | Installation and interior construction continues. |
| 1/16/07 | Installation and interior construction continues. |
| 1/12/07 | Package delivered and set. |
| 1/5/07 | Ready for package to be delivered. |
| 12/29/06 | Finishing up the foundation. |
| 12/22/06 | Foundation walls are up. |
| 12/15/06 | Footings complete. |
| 12/8/06 | Site clearing completed. |
| 12/1/06 | Site clearing nearly completed. |
| 11/24/06 | Driveway and footprint in. |
| 11/17/06 | Site clearing begins. |
| 10/27/06 | Pre-construction site. |