Roger & Martie O’Brien

   
Date Posted Summary
  Go to post-construction photos.
3/12/08 A few more finishing touches.
1/11/08 Ceiling fans, tub trim wall, various punch list items.
1/3/08 More finishing touches: light fixtures, etc.
12/28/07 Kitchen tile grouted, light fixtures installed.
12/14/07 Appliances installed, electricity is on, gate posts completed.
12/7/07 Tile work nearly complete. Gate footings poured.
12/1/07 Tile work coming along.
11/16/07 More finishing touches are complete.
11/10/07 Front stairs, deck, and railings complete. Interior railings in process.
11/2/07 Paving completed. Appliances delivered. More finishing touches.
10/27/07 More finishing touches.
10/19/07 Closets, shelves, finishing touches.
10/12/07 Countertop series.
10/5/07 Cultured stone and interior trimwork almost complete.
9/27/07 Down the home stretch with paint, cabinets and exterior work.
9/21/07 Cabinets, trim, and painting progress continues.
9/18/07 Cabinet and tile installation continues. Retaining wall is up.
9/13/07 Flooring and cabinet installation are in full swing.
8/31/07 Siding complete, interior painting under way.
8/23/07 Exterior siding going on, drywall installation continues.
8/17/07 Drywall is up, taping & mudding under way.
7/27/07 Interior rough-ins continue.
7/18/07 Electrical, plumbing, & HVAC rough-ins progressing.
6/30/07 Interior and exterior framing continues.
6/22/07 Roof shingles well along, and interior framing progress.
6/15/07 Roof sheathing & underlay finishing, interior framing continues.
6/8/07 Roof lines taking shape.
6/4/07 Framing continues upward.
5/25/07 2nd floor exterior walls going up.
5/18/07 Exterior walls coming along.
5/4/07 Ready to begin framing.
4/27/07 Foundation ready to have slab poured.
4/20/07 Under-slab rough plumbing & foundation wall water sealant application.
4/13/07 Concrete foundation walls up, forms removed.
4/6/07 Wall forms going up.
3/23/07 Footers poured.