John & Rose Simons

   
Date Posted Summary
8/20/08 Siding installation has resumed. More rough electrical changes.
8/12/08 Exterior cultured stone under way. More soffit framing for HVAC ductwork.
7/23/08 Security wiring nearly complete.
7/4/08 Interior framing/blocking, round mechanicals continue.
6/21/08 Rough mechanical, siding installation continues.
6/2/08 Fireplace framing, siding, etc., continues.
5/19/08 Rough electrical, siding being installed.
5/4/08 Rough mechanical, plumbing, and electrical installation continues.
4/26/08 Roof shingles are on. Rough mechanical ductwork installation is underway.
4/19/08 Deck framing well under way.
4/11/08 Framing continues.
4/4/08 Construction stairs to Lower Level and to above garage installed. Ceiling members installed.
3/23/08 Roof underlay being applied. Deck construction continues.
3/9/08 Roof framing and panel construction continues.
2/25/08 Roof framing continues to take shape.
2/16/08 Roof joists being attached.
2/12/08 The day the 3,500-lb. I-beam was set into place.
2/9/08 Exterior and interior framing and walls continue.
1/23/08 Main level exterior shape taking form. Garage is well under way.
1/11/08 Main level flooring and wall framing under way.
1/3/08 Lower Level panels and interior framing going up.
12/24/07 First truckload has been transferred up the hill. Second load has arrived.
12/14/07 Poured wall waterproofing under way. Framing to begin soon.
12/7/07 Rough under-slab plumbing in, ready for slab to be poured. First load of house package is staged.
12/1/07 Poured walls complete. Forms stripped.
11/16/07 Concrete wall forms nearing completion.
11/10/07 Footers all poured, rebar in place, ready to start walls.
11/2/07 Footer forms and rebar are well underway.